Project Timeline

The timeline below offers a broad overview of the Keybridge project, including proposed demolition and construction schedules and completion dates. Visit our news and updates page for more details of current and upcoming works or to download the most recent local community newsletter.

2015
 
Mar
Demolition Commence
 
Sep
Target Marketing suite and Show Home
 
2016
 
Jan
Substructure Commencement
 
Jul
Blocks B, C +D Commencement
 
Dec
Block F Commencement
 
2017
 
Feb
Block A Commencement
 
Sep
Block D - 10 Apartments
 
Nov
Block B1 - 47 Apartments
 
Dec
Block C - 81 Apartments
 
2018
 
Jun
Block B2 - 41 Apartments
 
Sep
Block F - 91 Apartments
 
2019
 
Apr
Block A - Section 1 - 60 Apartments
 
Jul
Block A - Section 2 - 62 Apartments
 
Aug
Block A - Section 3 - 49 Apartments
 